BHS Construction

Recent & Planned Work
The facilities at BHS have been drastically updated in recent years, and work continues thanks to ongoing bond issues and community support.
- Locker Rooms & Indoor Practice Facility
2009 will hopefully bring new locker rooms on the east side of the 2006 Bruin Field House and an indoor practice facility on the property once occupied by the Crestview Apartments, just across 18th Street from the Bruin Field House and the Fine Arts Center. - Stadium Sealant
The 1954 stadium has leaked for years due to problems with its inaccessible inner roof. During the summer of 2009 all of the bleachers will be removed so that a sealant can be applied to the concrete seating deck and there will be work on the expansion joints. Hopefully this will alleviate the infiltration problems. - Classroom Technology
Many classrooms now feature ceiling-mounted LCD projectors and sound systems. Plans are to finish incomplete installations from last summer and then, in the summer of 2009, equip most of the additional rooms. By 2010-2011 every classroom should have this technology. - New Lockers
The decrepit student lockers should finally be replaced in the summer of 2009 with wider double-tier units. - Future Bond Work
The 2007 bond issue will eventually fund additional renovations in the 2010-2013 timeframe: