Bartlesville High School:
Building on Excellence


Project Timetable

PhaseComponentsStart for DesignApprox. Bid TimeApprox. Completion Time
OneAthletic Fields, Parking, Environmental LabMay, 2001November, 2001August, 2002
TwoScience WingMay, 2001March, 2002Opened: July, 2003
Full Completion: May, 2004
Fine Arts CenterMay, 2001March, 2002Opened: August, 2004
ThreeField HouseJanuary, 2004
(Preliminary design May, 2001)
September, 2004Completed August, 2006
Library/Media Center & Connecting Link
(two rounds of bids rejected; rescheduled to phase four)
January, 2004
(Preliminary design May, 2001)
November, 2004
March, 2005
2006
FourLibrary/Media Center & Connecting Link & 1st Floor Restroom Renovations
(these projects finally accepted on 4th round of bids)
May, 2005April 2006
July, 2006
Fall 2007/Early 2008
HVAC Renovations
(omits 1939 field house and central portion of 1939 main building)
May, 2005 w/
multiple redesigns
November, 2006Fall 2007